I-75 Mill Creek Expressway


Home
About the Project
Members
Schedule
Archive
Alternatives
Related Links
FeedBack
Contact Information
FAQ

Welcome to the I-75 Mill Creek Expressway project website!

July 2011 Update:

Overall Project Update


Corridor Project Phasing and Schedule

Due to cost, constructability, and time constraints, the Mill Creek Expressway project has been split into eight phases of construction. The following table provides a brief description of each phase, major milestone dates, and current status:

Phase

Project Description

Construction Cost
(million)

Right-of-Way Acquisition
Start

Construction Start

Construction End

1

Mitchell Ave. Interchange

$53.6

Completed

Started

August 2014

Status

ODOT has acquired all Right-of-Way (R/W) for this project.  The design of this phase is complete.   

2

Monmouth St. Overpass

$7.1

Completed

Started

August 2011

Status

This phase is currently under construction.  The new Monmouth St. overpass is open to traffic.  Construction is currently centered at Bates Ave.  Entire project completion is scheduled for June 2011.  The Monmouth St. overpass phase is being funded through the American Recovery and Reinvestment Act.

3

Colerain/Beekman/I-74 Interchange

$12.1

Completed

May 2012

September 2012

Status

R/W acquisition for this project has been completed.  The design is complete.

4

I-75 from Western Hills Viaduct to Monmouth Overpass (includes Hopple Interchange)

$109.4

Started

March 2013

August 2016

Status

R/W acquisition has begun.  All R/W acquisition is schedule to be completed by May 2012.  The design is approximately 85% complete.  The next design milestone is due in June 2011.

5

I-75 from Monmouth Overpass to Mitchell Ave. (includes I-74 Interchange and I-74 improvements)

$150.2

January 2012

March 2015

August 2018

Status

Final design activities have begun.  Current design is approximately 50% complete.  The next design milestone is due in April 2011.

6

RR Overpass South of Norwood Lateral

$21.2

Started

March 2014

September 2015

Status

Design is approximately 85% complete.  The Stage 3 of 3 design milestone is due to be submitted in June 2011.  R/W acquisition has begun and is scheduled be completed by April 2013.

7

I-75 Mainline from Mitchell Ave. to the Norwood Lateral

$37.2

July 2011

March 2016

May 2018

Status

Design is approximately 60% complete.  The Stage 2 of 3 design milestone is due to be submitted in June 2011.  R/W acquisition is scheduled to begin in July 2011 and be completed by July 2014.

8

I-75 Mainline from the Norwood Lateral to Cross County Highway

$140.9

July 2013

March 2018

May 2020

Status

Final design activities are schedule to begin in Fall 2011.  Current design is approximately 30% complete.  The next design milestone is due in early 2012. R/W acquisition is scheduled to begin in July 2013 and be completed by April 2016.

8a

Seymour Avenue Overpass

$7.0

November 2012

April 2016

July 2017

Status

Final design activities are schedule to begin in Fall 2011.  Current design is approximately 30% complete.  The next design milestone is due in early 2012. R/W acquisition is scheduled to begin in November 2012 and be completed by November 2015.

9

Building Demolition Hopple/Colerain/Beekman Areas

$1.0

N/A

Started

December 2012

Status

Project is under construction.

Project Contact:
Stefan Spinosa, P.E.
The Ohio Department of Transportation, District 8
505 South SR 741
Lebanon, Ohio  45036
Phone:  513-933-6639
Email:  stefan.spinosa@dot.state.oh.us

 

Revive Cincinnati Effort:

ODOT is participating and assisting this City-led effort by providing information on our projects in the Hamilton I-75 corridor. As results and recommendations are adopted by the City, ODOT will work with the various partners to incorporate them when feasible.

 

 

 
   

What's  New?

Construction Information

now available.

Click link above for details...
________________

   
 


I-75 and Paddock
(photos by Larry Stulz)


I-75 & I-74

(photos by Larry Stulz)


Norwood Lateral

(photos by Larry Stulz)


Home | About the Project | Members | Schedule | Archive | Alternatives | Related Links | FeedBack | Contact Information | FAQ | Construction Information

 © Copyright 2009 TranSystems Corporation. All rights reserved.
For problems or questions regarding this Web site contact HAM75Webmaster@transystems.com.
Last updated: 01/04/11.