April 2012 Update:
Overall Project Update
Corridor Project Phasing and
Schedule
Due to cost, constructability, and time constraints, the Mill Creek
Expressway project has been split into eight phases of construction.
The following table provides a brief description of each phase, major milestone dates, and current status:
Phase |
Project Description |
Construction Cost
(million) |
Right-of-Way Acquisition
Start |
Construction Start |
Construction End |
1 |
Mitchell Ave. Interchange |
$53.6 |
Completed |
Started |
August 2014 |
Status |
Project is under construction. |
2 |
Monmouth St. Overpass |
$7.1 |
Completed |
Started |
Complete |
Status |
This phase is currently under construction. Minor work remains to be completed. |
3 |
Colerain/Beekman/I-74 Interchange |
$13.1 |
Completed |
May 2012 |
September 2014 |
Status |
Project is under construction. |
4 |
I-75 from Western Hills Viaduct to Monmouth Overpass (includes Hopple Interchange) |
$102.1 |
Started |
January 2013 |
August 2016 |
Status |
R/W acquisition has begun. All R/W acquisition is schedule to be completed by May 2012. The design is approximately 95% complete. Final plans are due in June 2012. |
5 |
I-75 from Monmouth Overpass to Mitchell Ave. (includes I-74 Interchange and I-74 improvements) |
$161.0 |
Started |
March 2015 |
August 2018 |
Status |
Final design activities have begun. Current design is approximately 70% complete. The next design milestone is due in August 2012. |
6 |
RR Overpass South of Norwood Lateral |
$19.9 |
Started |
March 2014 |
September 2015 |
Status |
Design is complete. R/W acquisition has begun and is scheduled be completed by April 2013. |
7 |
I-75 Mainline from Mitchell Ave. to the Norwood Lateral |
$37.2 |
Started |
March 2016 |
May 2018 |
Status |
Design is approximately 90% complete. The final design milestone is due to be submitted in May 2012. R/W acquisition is scheduled be completed by July 2014. |
8 |
I-75 Mainline from the Norwood Lateral to Cross County Highway |
$140.9 |
December 2013 |
March 2018 |
May 2020 |
Status |
Final design activities have started. The next design milestone is due in July 2012. Current design is approximately 50% complete. R/W acquisition is scheduled to begin in December 2013 and be completed by April 2016. |
8a |
Seymour Avenue Overpass |
$6.3 |
April 2013 |
April 2016 |
July 2017 |
Status |
Final design activities have started. The next design milestone is due in September 2012. Current design is approximately 65% complete. R/W acquisition is scheduled to begin in December 2013 and be completed by November 2015. |
9 |
Building Demolition Hopple/Colerain/Beekman Areas |
$1.0 |
N/A |
Started |
December 2012 |
Status |
Project is under construction. |
Project Contact:
Stefan Spinosa, P.E.
The Ohio Department of Transportation, District 8
505 South SR 741
Lebanon, Ohio 45036
Phone: 513-933-6639
Email: stefan.spinosa@dot.state.oh.us
Revive Cincinnati
Effort:
ODOT is participating and assisting this City-led effort by
providing information on our projects in the Hamilton I-75 corridor.
As results and recommendations are adopted by the City, ODOT will
work with the various partners to incorporate them when feasible.