January 2010 Update:
Overall Project Update
The project environmental document was approved by the Federal
Highway Administration in May 2009. Work on various phases is
progressing. The first phase of work is scheduled to begin
construction in the spring of 2010. This phase will construct the
new Monmouth Street connection between Central Parkway and Colerain
Avenue. ODOT has begun the Right-of-Way acquisition process on the
first four phases in the corridor. Design of the Mitchell Ave. phase
and Colerain/Beekman phases will be completed in August 2010. Hopple
Street interchange phase design is approximately 50% complete. Phase
6 design is approximately 40% complete. Final design of phases 5 and
7 is scheduled to begin in spring 2010. At this time, construction
and design funding for phase 8 has not been identified.
Phase 2, the Monmouth overpass phase, is being funded through the
American Recovery and Reinvestment Act.
Corridor Project Phasing and
Schedule
Due to cost, constructability, and time constraints, the Mill Creek
Expressway project has been split into eight phases of construction.
The following table provides a brief description of each phase and
tentative major milestone dates:
|
Phase |
Project Description |
Construction Cost (million) |
Right-of-Way Acquisition Start |
Construction Start |
Construction End |
|
1 |
Mitchell Ave. Interchange |
$57.7 |
Started |
March 2011 |
August 2014 |
|
2 |
Monmouth St. Overpass |
$7.1 |
Started |
April 2010 |
October 2011 |
|
3 |
Colerain/Beekman/I-74 Interchange |
$8.8 |
Started |
May 2011 |
September 2012 |
|
4 |
I-75 from Western Hills Viaduct to Monmouth Overpass
(includes Hopple Interchange) |
$99.6 |
Started |
March 2013 |
August 2016 |
|
5 |
I-75 from Monmouth Overpass to Mitchell Ave. (includes I-74
Interchange and I-74 improvements) |
$150.2 |
October 2011 |
March 2015 |
August 2018 |
|
6 |
RR Overpass South of Norwood Lateral |
$21.4 |
August 2010 |
March 2014 |
September 2015 |
|
7 |
I-75 Mainline from Mitchell Ave. to the Norwood Lateral |
$39.1 |
July 2011 |
March 2016 |
May 2018 |
|
8 |
I-75 Mainline from the Norwood Lateral to Cross County
Highway |
$148.1 |
August 2014 |
March 2018 |
May 2020 |
City of Cincinnati Revive I-75
Effort:
ODOT is participating and assisting this City led effort by
providing information on our projects in the Hamilton I-75 corridor.
As results and recommendations are adopted by the City, ODOT will
work with the various partners to incorporate them when feasible.
May 2009 Update:
Finding advances Mill Creek
Expressway Project
Recent action by the Federal Highway Administration advances ODOT’s
commitment to addressing the transportation needs of southwest Ohio.
A Finding of No Significant Impact (FONSI) issued by the Federal
Highway Administration enables ODOT to move forward with project
development of the $664 million Mill Creek Expressway. This action,
taken at the request of ODOT, is the culmination of nearly five
years of environmental and engineering analysis of a portion of
Interstate 75 in Hamilton County.
Click here for FONSI.
Approximately eight miles in length, the Mill Creek Expressway
project will improve traffic flow and enhance safety of Interstate
75 from the Western Hills Viaduct to north of the Paddock Road
interchange. Work will rehabilitate existing lanes as well as
construct an additional lane in each direction. The project also
includes modernization of the interchanges at Hopple Street, I-74,
Mitchell Avenue, Norwood Lateral, and Paddock Road as well as the
modernization of the Colerain Avenue/Beekman Street interchange with
I-74.
In issuing the FONSI, Federal Highway has determined that this
proposed reconstruction of I-75 will not have significant impact on
the human or natural environment.
“These projects do more than improve the freeway system. It will
modernize a vital link in our state’s growing transportation system
unlocking the potential for further economic development and new
jobs,” said District 8 Deputy Director Hans Jindal.
ODOT has begun the final design efforts and right-of-way acquisition
for various phases of work. It is anticipated that the first phase
of construction will begin in the Spring of 2010, and the final
phase will be completed in the Fall of 2020.
Listed below is the most up-to-date information. Construction
costs are based upon 2008 dollars.
|
Phase |
Project Description |
Construction Cost
(million) |
Right-of-Way Acquisition
Start |
Major Construction Start |
Major Construction End |
|
1 |
Mitchell Ave. Interchange |
$68 |
Jun 2009 |
May 2011 |
July 2013 |
|
2 |
Monmouth St. Overpass |
$6.5 |
Jun 2008 |
Mar 2010 |
Oct 2011 |
|
3 |
Colerain/Beekman/I-74
Interchange |
$11.7 |
Jan 2010 |
Mar 2011 |
Sept 2012 |
|
4 |
I-75 from Western Hills
Viaduct to Monmouth Overpass (includes Hopple
Interchange) |
$119 |
Sept 2010 |
Mar 2013 |
Oct 2015 |
|
5 |
I-75 from Monmouth
Overpass to Mitchell Ave. (includes I-74 Interchange
and I-74 improvements) |
$193.7 |
Nov 2011 |
Mar 2015 |
Apr 2018 |
|
6 |
RR Overpass South of
Norwood Lateral |
$27.9 |
Sept 2010 |
Mar 2014 |
Sept 2015 |
|
7 |
I-75 Mainline from
Mitchell Ave. to the Norwood Lateral |
$51 |
May 2012 |
Mar 2016 |
May 2018 |
|
8 |
I-75 Mainline from the
Norwood Lateral to Cross County Highway |
$186.5 |
Aug 2014 |
Mar 2018 |
May 2020 |
February 2009 Update:
Public Hearing Notice
Public Hearing Handout
Comment
Sheet
Exhibits
The Ohio Department of Transportation (ODOT)
encourages the public to attend a public hearing for the proposed
reconstruction of I-75 from the Western Hills Viaduct to Paddock
Road interchanges. The proposed project is located in the City of
Cincinnati, City of St. Bernard, and Village of Elmwood Place,
Hamilton County, Ohio. The hearing will be held Tuesday, February
10, 2009 from 4:00 to 7:00 p.m. at the St. Bernard Municipal
Building at 120 Washington Avenue, St. Bernard, Ohio 45217. The
hearing will be in an “open house” style and no formal presentations
will be made. You may visit at any time to view the project
materials and ask questions.
The purpose of the hearing is to inform the
public about the project, and encouraged the public to comment and
ask questions. Maps, drawings, and other pertinent information,
including the Environmental Assessment and previous project
documents, will be available for public inspection. During the
hearing the public will be able to discuss the project in an
informal matter with ODOT officials along with representation from
TranSystems Corp., who conducted the study. Comments will be
received either written or verbally (by a recorder), and will become
part of the official public hearing record. The comments will be
considered when making future project related decisions.
The proposed scope of the project includes
adding one additional through lane in each direction on I-75 from
the Western Hills Viaduct to north of the Paddock Road interchange.
The project length is approximately 8 miles. It also includes
improvements to the interchanges on I-75 at Hopple Street, I-74,
Mitchell Avenue, Norwood Lateral (SR 562), and Paddock Road. The
partial interchange at Towne Street is removed by the project. The
Colerain/ Beekman interchange on I-74, just west of the I-74/I-75
interchange, is improved as a part of this action.
The tentative schedules for right-of-way
acquisition and construction will be available, and ODOT's Southwest
District right-of-way officials will be on hand to answer questions.
Tentative schedules for the start of right of way acquisition and of
construction are dependent upon federal approvals.
Copies of the Environmental Assessment which
documents the purpose and need of the project along with the
anticipated social, economic, and environmental impacts can either
be viewed on the website (see links on the right side of this page)
or at the following locations during business hours:
Ohio
Department of Transportation
District 8 Offices
505 S.
State Route 741
Lebanon, OH 45036
Cincinnati City Hall
801
Plum Street
Cincinnati, OH 45202
St.
Bernard City Hall
110
Washington Avenue
St.
Bernard, OH 45217
Elmwood
Place Village Hall
6118 Vine Street
Cincinnati, OH 45216
Camp
Washington Community Center
1201
Stock Avenue
Cincinnati, OH 45225
Cincinnati Public Library
Downtown Main Branch
800 Vine Street
Cincinnati, OH 45202
Clifton Branch
351 Ludlow Avenue
Cincinnati, OH 45220
Elmwood Branch
6120 Vine Street
Cincinnati, OH 45216
Northside Branch
4219 Hamilton Avenue
Cincinnati, OH 45223
St. Bernard Branch
4803 Tower Avenue
Cincinnati, OH 45217
General
project questions can be addressed by Stefan Spinosa, ODOT’s Project
Manager, at 1-800-831-2142. Comments can be mailed, prior to the
close of the public comment period on February 26, 2009, to Ohio
Department of Transportation, Keith Smith Acting District 8 Planning
and Environmental Engineer, 505 South State Route 741, Lebanon, Ohio
45036. Individuals with a disability who need a reasonable
accommodation to participate in this event please contact Keith
Smith at 1-800-831-2142 by February 3, 2009.
November 2008 Update:
Hopple Interchange Decision
Making Process
In July, 2008 the Cincinnati City Council passed a resolution which
stated a desire for ODOT to evaluate additional alternatives at the
Hopple Street Interchange. During ODOT’s Value Engineering (VE)
session, which is part of ODOT’s Project Development Process, three
additional alternatives were discussed at Hopple. Each of those
three alternatives, along with the previously Recommended
Alternative, was anticipated to be evaluated based upon the
evaluation criteria determined by the Implementation Committee (IC)
members at the August 27, 2008 meeting.
VE Alternatives
(link)
·
VE Alternative 1: Double Roundabout Diamond Interchange (with
roundabout at MLK/Central Pkwy)
·
VE Alternative 2: Partial Cloverleaf with traditional
at-grade intersection at Central Parkway/MLK
·
VE Alternative 3: Previously Recommended Alternative with
I-75 northbound on-ramp moved opposite off-ramp
NOTE: The recommended alternative (as of August 2008) and the
three VE session alternatives are displayed in HOP_alts.pdf. It
should be noted that each of the three VE session alternatives were
conceptual at this stage and required additional engineering and
traffic analysis. It was anticipated that analysis would likely
change the layout and/or footprint of the interchange and adjacent
streets.
Evaluation Criteria
In order to properly evaluate the alternatives, the IC members were
asked to review the existing criteria and make additions or
modifications. Several of these additions or modifications were
incorporated into the evaluation criteria below. Additional items
that are not listed below, but will be incorporated into the
evaluation include; (1) emergency vehicle access, (2) amount of
surplus property (future development opportunities), (3) grade of
slopes following construction, (4) appearance of bridge(s)/road(s),
(5) exploring lower speeds on Hopple, (6) visibility for
communities/businesses, and (7) street connectivity.
At the end of the meeting, each of the IC members were given four
stickers to place on a sheet listing the evaluation criteria. They
were permitted to use their four stickers, representing their
priorities, in any combination (such as all four on one criterion).
The number of votes is listed next to the evaluation criteria below.
Safety (3 votes)
A broad measure of relative safety performance of the alternative
based upon such factors as interchange spacing (mainline), traffic
weaving and other vehicle interactions, historical evidence, and
engineering judgment.
Mobility (19 votes – 3 specifically for Congestion Mitigation and
3 specifically for Regional Mobility)
The operational performance of the alternative in terms of expected
level of service, ease of providing local access opportunities, and
promotion of traffic moving through the network. The mobility rating
is subdivided into the following three categories:
·
Congestion Mitigation - A measure of the predicted level of
service and operational efficiency of the alternative.
·
Local Access - Ease and convenience of local access
opportunity. For interchange alternatives, the rating provides an
indication of whether the interchange is full or partial, or whether
the alternative gives improved arterial operation.
·
Regional Mobility - For interchanges, this measure is an
indication of expected congestion on the freeway caused by poor
interchange performance.
Environment (5 votes)
This category is included as a broad indication of expected
environmental impacts generated by the alternative.
·
Air Quality – Higher congestion and stop-n-go operation
generate higher levels of emissions
·
Noise – Higher traffic volumes and elevated roadways increase
noise levels
·
Cultural Resources – Impacts to historic properties eligible
for the National Register of Historic Places
·
Ecological Resources – Impacts to wetlands, streams, and
habitat
·
Hazardous Materials – Impacts to properties contaminated with
regulated substances or waste
Community (18 votes – 2 specifically for Development Benefits and
2 specifically for Parks and Recreation Areas)
Impacts to communities are summarized by the following
subcategories:
·
Development Benefits – A measure of improved local access,
increase/decrease in developable lands, and negative impacts of
relocating businesses.
·
Context Sensitive Design – This rating indicates relative
negative visual impact of the alternative, opportunity for aesthetic
treatment, and how well the alternative fits the site.
·
Facilities and Services – Impacts to public facilities and
services, community buildings
·
Parks and Recreation Areas – Impacts to parks, playgrounds
and recreation centers
Modes (22 votes – 2 specifically for Transit, 3 specifically for
Freight, and 2 specifically for Bicycle)
This category evaluates the alternatives’ performance in
accommodating non-vehicular travel.
·
Transit – impacts to or enhancement of bus or rail transit
use
·
Freight – impacts to or enhancement of freight rail
·
Bicycle – impacts to or enhancement of bicycle travel
·
Pedestrian – impacts to or enhancement of walkability
Displacements (1 vote)
This category evaluates impacts on property owners, businesses, and
residents.
·
New right-of-way required – Amount of property to be
purchased
·
Residential relocations – Number of households displaced
·
Business relocations – Number and type of businesses
displaced
Cost (4 votes)
Estimated total project cost
·
Right-of-Way – Costs for right-of-way purchase and
relocations
·
Construction – Includes construction costs
·
Life Cycle – Cost to maintain constructed infrastructure.
This is a relative measure that is dependent on extent of built
structures such as bridges and retaining walls.
Construction (8 votes – 1 specifically for MOT and 4 specifically
for duration)
Impacts during construction
·
Maintenance of Traffic (MOT) – access during construction
·
Duration
·
Construction Noise
Alternatives Evaluated
Following the August 27th IC meeting, the project team
further evaluated the feasibility of the three VE alternatives.
Once the analysis of each alternative was completed, the project
team met with ODOT and the City of Cincinnati to discuss the
findings. The analysis for each alternative is summarized as
follows:
VE Alternative 1: Double Roundabout Diamond Interchange (with
roundabout at MLK/Central Pkwy)
·
The 2-lane roundabouts failed operationally in the opening
year. A substantial backup of roughly 800 feet west along Hopple
was observed in the model. The backup extended through interchange
roundabouts, therefore blocking exiting traffic and causing backups
along the interchange ramps back to mainline I-75.
·
In order to operationally make this alternative function,
three lanes were necessary at each roundabout and considerable
distance was necessary between the two roundabouts on the eastern
side of the interchange.
·
Property impacts were greater under this alternative than the
previously Recommended Alternative.
·
MLK has a grade of 8% approaching the roundabout. Typically,
steep grades are a deterrent when evaluating potential roundabout
locations.
·
A three-lane roundabout is unusual. There are very few in
the country and none currently in Ohio. A roundabout of this type
has larger conflict zones. The safety performance of multi-lane
roundabouts drops substantially compared to single lane roundabouts.
·
Pedestrians may have concerns with multi-lane roundabouts
which require crossing 2 or 3 lanes at a time. Blind pedestrians
are particularly a concern and have been reported by Camp
Washington. Signalization may be necessary. The Access Board
currently has a lawsuit pending on this issue. There is presently
no direction from FHWA on how to address this issue, either as to
whether to signalize, and if so, what type of signal to use.
Signalization types for pedestrian crossings have been controversial
for roundabouts. Motorists may disregard signals that are merely
warning in nature; however, with a green/red signal, a green light
may lead motorists to ignore the yield line when entering the
roundabout.
VE
Alternative 2: Partial Cloverleaf with traditional at-grade
intersection at Central Parkway/MLK
·
This alternative failed operationally in the opening year.
The MLK/Central intersection was too close to the interchange
creating backups. Additionally, there was a substantial backup of
roughly 2,000 feet along Central Pkwy (north of City property).
·
In order to operationally make this alternative function, the
MLK/Central intersection needed to be moved further east and up the
hill. This would create several additional property impacts.
Furthermore, the grade would be 8% or greater on Central to meet MLK
at a new intersection.
·
Additional lanes would also be necessary along MLK to make
the intersection with Central function. There still would be
considerable backup along Central Pkwy.
VE
Alternative 3: Previously Recommended Alternative with I-75
northbound on-ramp moved opposite off-ramp
·
This alternative was a modification of the previously
Recommended Alternative and moved the northbound I-75 on-ramp (from
the MLK/Connector Road intersection) to line up with the northbound
I-75 off-ramp.
·
This alternative operated adequately in the opening and
design years and lowered the impacts (3 acres less) over the
previously Recommended Alternative.
Recommended Preferred Alternative
(Link)
During the August 27th IC meeting, members established
evaluation criteria for the project team to rank the alternatives.
After the alternatives were evaluated and presented to the City
Staff, Cincinnati City Council passed
Resolution
53-2008 supporting VE Alternative 3 and urging ODOT to eliminate
Alternatives 1 and 2. Therefore, a substantial alternative
evaluation using the previously identified criteria was
unnecessary. VE Alternative 3 was chosen as the Recommended
Preferred Alternative.
Benefits of VE Alternative 3 over
the Current Situation (existing conditions)
·
Removal of the left hand exit which causes accident problems
and is an overall safety issue
·
Removal of the Partial interchange
o
Bates on-ramp only goes to I-74
o
Central Pkwy. ramp for I-75 northbound
o
Confusion with the partial interchange and separation of
ramps
·
Hopple/Central/MLK intersection currently operates at a very
poor level of service
·
VE Alternative 3 will preserve future Light Rail Corridor
·
VE Alternative 3 will add sidewalks and streetlights along
both sides of Hopple