March 2008 Update
Overall Project Update:
The project team is completing the
Preferred Alternative Verification for the I-75 corridor from the
Western Hills Viaduct to just north of Paddock Road. This effort
also includes alternative development for I-74 from the
Colerain/Beekman exit to I-75. This step of the process refined the
design of the recommended alternative established after public input
between September 2006 and April 2007. The design plans have been
submitted for review to ODOT and FHWA. This review should be
completed by the end of February. The project team is also
preparing the first draft of the Environmental Document. This
document and the information on the Preferred Alternative will be
presented at a Public Hearing to be scheduled in May of this year.
Preferred Alternative Design
Displays:
The Preferred Alternative can be
viewed on the Alternatives
page.
Corridor Project Phasing and
Schedule:
Due to cost, constructability, and
time constraints, the Mill Creek Expressway project has been split
into eight phases of construction. The following table provides a
brief description of each phase and tentative major milestone dates:

February 2008 Noise Wall Meeting Information
In an effort to gather public input to determine a
desire for noise barriers in conjunction with the I-75 Mill Creek
Expressway widening project, the Ohio Department of Transportation,
in cooperation with TranSystems Corp., conducted two public meetings
concerning several recommended noise barriers along I-75, I-74 and
State Route 562. The meetings took place on February 26 and 27,
2008 and were intended for those residents and property owners who
would be directly affected and could benefit by construction of
noise barriers. In addition, the meetings were held to gather
suggestions regarding the appearance of the proposed wall. In
accordance with the noise abatement program, only the comments of
those who are expected to receive a sound-level benefit from the
installation of a noise barrier will be considered in the decision
on whether or not that barrier will be constructed.
Meeting
exhibits can be viewed at:
http://www.dot.state.oh.us/dist8/planning/PI%20meetings.htm
Comments
may be submitted by mail until March 27, 2008 to Ohio Dept. of
Transportation – District 8, 505 South State Route 741, Lebanon, OH
45036 Attn: Stefan Spinosa.
June 2007 Update Document
The
I-75 update document summarizes the steps taken to date and
the decisions made with respect to the Mill Creek Expressway
Feasible Alternatives. This update includes changes to the Feasible
Alternatives, following the Mach 29, 2007 public meeting, as a
result of public input.