Timeline for Project Milestones

Fall/Winter 2003
Project Ranked High from NSTI
Spring 2004
Funding Identified and Programmed thru TRAC
Fall 2004
ODOT Assembles Consultant Team and Implementation Committee
Fall/Winter 2004/2005

Technical Studies Conducted

Spring 2005 Fall 2007

Identify Various Alternatives

Fall 2007 Winter 2008/2009
Determine Final Alternative / Project Phasing
Spring 2010 Spring 2020
The following table provides a brief description of each phase and tentative major milestone dates:

 

Phase

Project Description

Construction Cost

(million)

Right-of-Way Acquisition

Start

Construction Start

Construction End

1

Mitchell Ave. Interchange

$53.6

Completed

Started

August 2014

2

Monmouth St. Overpass

$7.1

Completed

Started

August 2011

3

Colerain/Beekman/I-74 Interchange

$12.1

Completed

May 2012

September 2012

4

I-75 from Western Hills Viaduct to Monmouth Overpass (includes Hopple Interchange)

$109.4

Started

March 2013

August 2016

5

I-75 from Monmouth Overpass to Mitchell Ave. (includes I-74 Interchange and I-74 improvements)

$150.2

January 2012

March 2015

April 2018

6

RR Overpass South of Norwood Lateral

$21.2

Started

March 2014

September 2015

7

I-75 Mainline from Mitchell Ave. to the Norwood Lateral

$37.2

July 2011

March 2016

May 2018

8

I-75 Mainline from the Norwood Lateral to Cross County Highway

$140.9

July 2013

March 2018

May 2020


I-75 and Norwood Lateral

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Past Schedule 

Step 1: Problems, Needs and Goals (completed December 2004)

         Study Area Boundary

         Stakeholders Identified

         Public Involvement Plan 

Step 2: Conduct Technical Analyses (completed May 2005)

         Logical Termini

         Red Flag Report

         Purpose and Need Report

         Existing and Future Conditions Report

Step 3: Conceptual Alternative Solutions (completed June 2005)

         Conceptual Alternative Solutions Identified

         Conceptual Alternative Solutions Evaluation

Step 4: Planning Study Report (completed June 2005)

         Planning Study Report Document

Step 5: Develop Conceptual Alternatives (completed March 2006)

         Public Meetings

         Conceptual Alternatives Study

Step 6: Refine Feasible Alternatives (completed January 2007)

         Assessment of Feasible Alternatives Document

         Public Meeting(s) 

Step 7: Develop Preferred Alternative (completed January 2008)

         Preferred Alternative Verification Document (PAVR)

Step 8: Prepare Environmental Clearance (completed January 2009)

         Environmental Document (EA)

 


Home | About the Project | Members | Schedule | Archive | Alternatives | Related Links | FeedBack | Contact Information | FAQConstruction Information

  Copyright 2009 TranSystems Corporation. All rights reserved.
For problems or questions regarding this Web site contact HAM75Webmaster@transystems.com.
Last updated: 02/10/09.